Moreno Valley USD Facilities Department 16.11.2020

MORENO VALLEY HIGH SCHOOL: CULINARY ARTS; IMPROVEMENTS TO LECTURE HALL: Construction is estimated to start mid-November 2020. Architect: WLC Contractor: Neff Construction... For additional information, please view our Website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 03.11.2020

MORENO VALLEY HIGH SCHOOL: MODERNIZATION OF BUILDINGS B, C, D, E, AND F; UPGRADED CTE WELDING SHOP Construction started in May 2020. Special Education classrooms are complete. Science Labs, art/ceramics studios and new kiln room will be completed by November 2; along with the welding shop, wrestling room and team room.... Building B started demolition. Architect: WLC Contractor: Neff Construction Measure M project; Welding Shop CTE Grant For additional information please visit our Website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 25.10.2020

PERRIS OPERATIONS CENTER: PARKING LOT EXPANSION AND CONSOLIDATED ELECTRIC METERS Project is 90% complete! Solar Panels are up: providing cost savings and shaded additional parking; Motorized gates are installed with remote operating feature; Numerous electric meters have been consolidated in to new switchgear;... Final paving and striping of south lot will be completed in October. For additional information please see our Website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 13.10.2020

MORENO VALLEY HIGH SCHOOL: NEW PERFORMING ARTS CENTER Construction started in August 2019. Project is 60% completed. Architect: John Sergio Pisher... Contractor: Neff Construction Measure M Bond Project Estimated Completion: April 2021 For additional information, please view our Website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 23.09.2020

RIDGECREST Elementary: Bus/Parent Drop Offs - PROJECT IS COMPLETE! Closed out in June 2020

Moreno Valley USD Facilities Department 21.09.2020

VALLEY VIEW H.S. Gym Modernization: Current. UPDATED 9/22/2020: Completed Items: Flooring, HVAC and Roof, Restrooms, Paving. Still in progress: Painting, Bleachers, Landscaping. Estimated Completion is still October 2020.

Moreno Valley USD Facilities Department 13.09.2020

BUTTERFIELD Elementary Bus/Parent Drop Offs: CURRENT UPDATED: 9/22/2020: This project is SUBSTANTIALLY COMPLETED. Final cleanup and punch-walk remaining.

Moreno Valley USD Facilities Department 02.09.2020

SUNNYMEADOWS Elementary Head Start and Shade Structure. The Shade Structure is installed/complete. Renovation of portable to accommodate a new Head Start facilities is currently pending funding availability. Architect: PCH If you would like more info, please view our website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 28.08.2020

VALLEY VIEW H.S. NEW 2-STORY BUILDING. Currently under review with the Department of State Architect (DSA) - near approval. Architect: Ruhnau Clarke; Constractor: Tilden-Coil For more additional information, check out our website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 13.08.2020

SUNNYMEAD MIDDLE MODERNIZATION (Buildings A, B, C, D and F). Project has been approved by the Department of State Architect (DSA). Construction is yet to be determined. Architect: PJHM; Contractor: Tilden-Coil. For additional information please view our webpage: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 04.08.2020

SUNNYMEAD MIDDLE NEW MPR and Conversion of Existing MPR to a VAPA Building. This project is currently under review by the Department of State Architects (DSA). Contractor is: Tilden-Coil; the Architect is: PJHM. UPDATED 9/22/2020: Attached are 3 graphics depicting the concept of the new MPR. For additional information please go to our webpage: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 24.07.2020

ELEMENTARY SCHOOL SITE FENCING UPDATED 9/22/2020: This is a current project that is 90% complete. Chain-link fencing for perimeter and kindergarten is 100% Complete. Ornamental fencing is 85% complete. Block wall for kindergarten plan area is complete. For additional information, please check out our website: https://www.mvusd.net/apps/pages/index.jsp

Moreno Valley USD Facilities Department 05.07.2020

Canyon Springs HS Modernization of Existing Campus: Current Modernization of Buildings A and D to include admin area, classrooms, science labs, new hard courts, and removal of portables. UPDATED: 9/22/2020: Buildings A and D to start in January 2021; Temporary administration offices are near completion. Architect: HMC Architests... Contractor: Tilden-Coil For additional information, please visit our Facilities Website: https://www.mvusd.net/apps/pages/Facilities See more

Moreno Valley USD Facilities Department 01.07.2020

Canyon Springs H.S. CTE Cyber Security: Future Project Conversion of existing auto and wood shops in to a fully equipped lab and classroom setting for Cyber Security innovation and application. DSA approved. CDE (CA Dept of Education) and CTE (Career Tech Education) have completed their review with high scores, which improves the possibility of funding If funding available, construction should start Summer 2021... Architect: HMC Architect Contractor: Tildon-Coil Construction For more information, please visit our Facilities WebPage: https://www.mvusd.net/apps/pages/Facilities See more